The regulator’s decision puts one type of contract at risk, but won’t close the door on nuclear power plants looking to sign ...
Last week, the Federal Energy Regulatory Commission voted against Talen’s request for ... build a data center campus with a ...
While owners of nuclear power plants had been hoping they could look to tech companies to sell their power, a ruling from the Federal Energy Regulatory Commission could throw a wrench in those plans, ...
The US Federal Energy Regulatory Commission (FERC) has rejected a proposal that would have allowed an Amazon data centre ...
The proposal would have boosted the amount of electricity coming from the Pennsylvania power plant from 300 megawatts to 480 ...
Nuclear plant owner Talen Energy Corp. says an initial 300 MW of data center development can proceed despite feds' rejection of grid link agreement to its Susquehanna facility in Pennsylvania's ...
Talen Energy Corp and other US power company stocks slumped in pre-market trading Monday following the rejection by the ...
Tech giants looking to quickly power massive artificial intelligence (AI) centres will need to come up with new strategies ...
Constellation believes narrow reforms are required to provide clarity, fair pricing, and price stability for customers and ...
The Federal Energy Regulatory Commission (FERC) rejected an effort Friday to allow an Amazon data center to tap into ...
Amazon’s (NASDAQ:AMZN) plan to build a data center powered by a Pennsylvania nuclear power plant has not changed, even as the ...